Featured Project
Sievert Crane & Hoist served as the Prime Contractor for the Mississinewa overhead crane replacement project commissioned by the USACE Louisville District.
Contact UsThe project involved replacing the existing controls, trolley, and bridge drives, as well as handling the lead and asbestos abatement associated with it.
A challenge was presented as the project required designing a 140 ft long lift 20 Ton hoist trolley unit that could fit in a very tight headroom condition. Additionally, the team designed a new bridge drive and a full new catwalk for the crane, along with new VFD controls.
The installation was done in the air without removing the crane, and completed entirely by Sievert’s crew of union ironworkers, electricians, and hoist technicians. The final stage involved load testing with water weights on-site.
Sievert Crane & Hoist is ready to help you with your next project. Contact us to request a quote or get answers to your questions.